Setting Foundation Walls

After the footings were poured, started right away with setting the forms for the walls.  It took a bit longer than expected because the foundation guy was juggling a couple things but we were only a couple days behind original plan.

All walls set except for the beast wall in the corner.



Passed inspection with three items to be rechecked at a later date but we were able to continue with the pour the following day.  Pump truck arrived and set up as close to the perimeter as he could.  The hose just barely reached the opposite corner at the far end of the house.

Just one of the many trucks that were constantly rolling in and out for a couple hours.





Mark working the hose and Justin working the trowel.