Sunday, June 9, 2013

Setting Foundation Walls

After the footings were poured, started right away with setting the forms for the walls.  It took a bit longer than expected because the foundation guy was juggling a couple things but we were only a couple days behind original plan.

All walls set except for the beast wall in the corner.



Passed inspection with three items to be rechecked at a later date but we were able to continue with the pour the following day.  Pump truck arrived and set up as close to the perimeter as he could.  The hose just barely reached the opposite corner at the far end of the house.

Just one of the many trucks that were constantly rolling in and out for a couple hours.





Mark working the hose and Justin working the trowel.











Friday, June 7, 2013

Got Power

Got the call from the electric company that they would be turning on the power sometime today but couldn't give me a timeframe.  I had dumped 10yd of sand by the temp pole pit but had to take some by the transformer pit so I got there early to move about 4yd.

The power company showed up first thing and got right to work.

The three lines were big and filled up the 3" pipe.  They attached the cables to the 250' rope I had to leave inside the conduit and the guy on the other end started to pull.

Even though there was only one slight bend, about 22 degrees, he was still pulling hard to get that wire through the conduit.  I jumped in and helped him pull for about the last 100' so that was pretty cool.  I wanted to get some pictures of them actually connecting up the wires but the lumber salesman showed up to go over the upcoming first load.  By the time I finished up, they were already done and packing up.

I then filled in both pits with sand and checked the meter .... it shows all 0000s.  Pretty sweet.

We now have power and don't have to worry about taking generators back and forth.

Monday, June 3, 2013

Excavation Mods and Electrical Inspection

After Mark was setting up the footings forms, there were two areas that needed additional excavation so I was able to take care of it and now can say that excavation was one of the many trades that I ended up doing :-)

Here's the view looking down to one of the marked out areas that I need excavate.

Even though I had a long arm on the mini, I couldn't quite get too close to the edge as it would exert too much pressure on the walls and possibly cave in.  Thus, I had a lot of manual digging.  I pulled out as much as I could with the mini and then shoveled the rest into the bucket and then climbed back up to to dump it.  That was definitely a workout.

 The remote temp pole needs to be inspected by L&I before the electrical company will hook up temporary power.  The first time I failed because the meter box I'm using (provided by framer) is an above ground only and I fed the service lines from the bottom.  The electrical connections were correct but the wires had to enter from the top even though the power is coming from below ground.

I had already purchased the wire (3) 2 AWG and didn't have alot of excess so I had to try and route from top while still leaving the minimum required by electrical company (they wanted 5').  I used (2) LB connectors and some conduit to piece it together.  It wasn't pretty, actually really ugly and it truly bugs me because I'm kind of an neat and orderly person.  I call it frankstienish but the inspector said it just has to be functional.  So be it, I called again and this time it passed so I should have power within 5-10 days.


I also worked some more on the silt fence and have about 180' installed, staked, stapled, and backfilled.  I'm just waiting for the first deer or elk to rip it apart.


Foundation Footings

Well, we received the permit so we now can move ahead with the foundation!!  It took about 5 weeks to get it so that was pretty fast and there were only a couple issues to be addressed.  The engineer had to write a letter to justify the snow load calculation and the designer had to to add a CO detector and insulation under the stairs.

The foundation guy, Mark, is ready to go and setting up the boards for the footings.




The soils up here are amazing and even after raining for a week, there are no puddles except for one small area that is compacted from the trucks.  This means no run off or erosion but the county still wants to have a drainage plan that is engineered ($1000) and pay them a drainage fee ($1900).

I used the 12" bucket on the excavator to dig a shallow trench to install the silt fence to prevent erosion ... which I will bet I never get any dirt built up against the fence.


Even though the silt fence comes up stakes at 10' apart, the county requires wooden 2"x2" stakes every 3'.  I  purchased 8' fir boards, cut them in half, and then cut angles to drive them in the ground.


Big Big Hole

Well, they finished in two days and I was completely amazed at how big the hole was and how much material was piled around.  I knew it would be big but this was crazy big.

The area is now ready for footings and pier pads



View from rear of house looking toward front












Sunday, June 2, 2013

Little Big Hole

The permit should be ready within a couple days but I went ahead with the excavation so we would be ready for foundation once I get it.  Dean and crew started about 8am and said they would be done by end of next day.  That is good news but they sure make bank ... to the tune of about $150/hr if they finish tomorrow.  Everyone says they are the best so that gives me assurance.

The day before, I marked out the house with the foundation guy but when Dean showed up, we had to remark as there was a mistake.



Cutting in for the basement


First cut completed


Close up of first cut completed





There was so much material moved that they moved about 100+ yds to fill in the driveway entrance.  This was awesome because the entrance and the house are same ground level but there is about a 2' dip in between.  Now it is a nice flat entrance all the way from the street to the house.

Spreading out material to raise driveway







Wednesday, May 22, 2013

Weekend Work 5.19.13

Couple of random updates ...

Have been trying to finalize a dirt guy and the best one around is Dean but his price is higher than I had allocated.  The foundation guy, Mark, highly recommends him and said he trucks him to job sites a couple hours away instead of using local because he is that good.

Well, John (our neighbor building behind us) has a friend (Craig) that does clearing for commercial sites and he said he would do it for about $1200 cheaper.  I was debating and finally decided to have him meet the foundation guy at the site before making decision.  After about 20min we were done and then John, Mark, and I headed over to John's property to take a look.  Mark expressed concerns about Craig's ability to 'convert thinking' from commercial to residential.  I decided to hire Dean ... will see if that is the right decision.

Can't recall if I have talked about the septic system but all the lots were originally approved for pressure systems .  Most people have been converting to gravity as it much cheaper to install and pretty much no maintenance (I just spent $1000 to replace a new pump and refurbish the whitewater pump in my current pressure system so).  Well, the soils out there are absolutely amazing and drain so fast which is also a problem for the drain fields.  So far all my neighbors have successfully converted to and received approval from the health dept for gravity .... not me or John though.  The new guy there said our soils are border line and could go either way [Note - this is all subjective when looking at the soil, nothing scientific or objective about it] so he decided against.  I went to visit him at the office and he said I could keep digging different perc holes until I found less rocky holes or I was stuck with pressure.  Great, another $3k

Since I'm waiting on house permit (workshop permit approved), I have been just working on cleaning up various areas toward the front of the property.  On the east side, there used to be an old fire road so we wanted to landscape it so it doesn't look like we have a side road leading into the property.  I planted six trees and will worry about cleaning the area up later.  I fell two more trees that looking pretty rough and then planted two more Leyland Cypress in place - still have four more to put in.