Here's C enjoying the view from her future office.
Two days later they sheeted the exterior and braced the walls. First rain but the wood really didn't get wet too bad. I changed to Doug Fir instead of Hemlock Fir (more costly) as it is the best structural lumber by far.
Meanwhile, I have so much backfilling to do that it will probably take me a couple months before everything is done. As I finish off sections of the waterproofing, I will try and move dirt but the biggest areas are the front of the house and the garage.
I have to raise up the the garage floor about 3' and for a 1300 sq ft area, that is a lot of material..
Plus the front of the house is excavated out about 15' away from foundation where the pier pads were poured. Once I pour the sonotubes, that will be about 50+ yds of dirt to fill in.
At least we are starting to see the house take shape now.