At this point, we are about 1-2 weeks behind schedule and that is primarily because the framer has multiple jobs going .... and one of those is for a job I recommended him for. When we were discussing prices and duration before giving him the nod, he said they would frame it in four weeks which was two weeks better than the other guys. Well, it will probably take him 4 weeks on being onsite but it will take 6-8 weeks of actual time based on the rate we're going. That aside, really like him and he is doing great work.
Looking up to the garage ceiling. We didn't put any post/beams in the garage, just clear span of trusses so the garage appears so massive. I will finally be able to park my truck inside.
The front of house seems to go on forever .... although J&Bs house that will be built 10 ac behind us is actually 26' longer. Crazy
Same shot, other side.
Looking out over the end of the covered porch
Sunset; hanging out on top of the house, nothing better :-)